Here are some pictures of the past week. All of the appliances are in and most of the plumbing is done. We still have a sink that needs to be installed in the girls bathroom (it came in damaged), the pedestal sink in the half bath and the shower fixture in the master bath. But...there is always a but...the plumber won't come back until the girls sink is put in...and the counter top guys who need to put the sink in are on vacation. Our closing next week rides on us getting the plumbing inspection early this week and then being able to get the final inspection late in the week. Awesome....doubt all of this will happen smoothly this week...
Also, the cabinet guys still need to come back and finish some things in the kitchen. Some of the toe kicks are missing and the back of the island piece was back ordered. Plus they need to install my furniture legs!
I was able to go to the house on Thursday of this week and started putting kitchen items in all the cabinets. Thanks Jen for helping (and bringing wine)! Although...she probably thinks I'm a hoarder after seeing all the crap I have... I am truly clueless as to how I fit it all in the old house.
The carpet is in. I am pleasantly surprised at how nice and soft the carpet is since its the builder grade. The true test is how it's going to hold up over the years...
Here is the spare room...
Sophie's room....
Liv's room (yes...I set up some toys in order to buy me time when I go there each week with the girls!).
The master bedroom...
The master closet and study...
And the master bath...
If we are to close next week...here are the items that still need to be done...
- the girls sink and plumbing needs to be installed and finished
- the master shower plumbing needs to be finished
- the half bath sink and fixtures need to be installed
- the refrigerator ice-maker needs to be plumbed (note: we are told that the above plumbing should only take a day)
- we need the plumbing inspection
- the hvac guy needs to come back and put all the vent covers on
- there is a leak in one window and in the attic were the hvac guy vented out the unit that needs to be addressed
- the plasterer needs to sand all the patch work he did
- the painters need to come back and basically give the entire house another coat because of the awful job they did
- the front walkway and under the deck needs to have the cement poured
- a cleaner needs to come in
- and we need a final inspection.
Seems like a lot to do in only a few days. And seeing how we NEVER see workers there simultaneously...I am guessing it's not going to happen. Great.
Merry Christmas everyone!